<?xml version="1.0" encoding="UTF-8"?>
<Project xmlns="http://schemas.microsoft.com/project">
  <SaveVersion>14</SaveVersion>
  <Name>118,000 SF Tilt-Wall Distribution Warehouse with Office Buildout</Name>
  <Title>118,000 SF Tilt-Wall Distribution Warehouse with Office Buildout</Title>
  <Author>Big State AI (BSA)</Author>
  <ScheduleFromStart>1</ScheduleFromStart>
  <StartDate>2026-07-20T08:00:00</StartDate>
  <FinishDate>2027-06-16T17:00:00</FinishDate>
  <CalendarUID>1</CalendarUID>
  <DefaultStartTime>08:00:00</DefaultStartTime>
  <DefaultFinishTime>17:00:00</DefaultFinishTime>
  <MinutesPerDay>480</MinutesPerDay>
  <MinutesPerWeek>2400</MinutesPerWeek>
  <DaysPerMonth>20</DaysPerMonth>
  <DefaultTaskType>1</DefaultTaskType>
  <DefaultFixedCostAccrual>3</DefaultFixedCostAccrual>
  <NewTasksEffortDriven>0</NewTasksEffortDriven>
  <NewTasksAreManual>0</NewTasksAreManual>
  <SpreadActualCost>0</SpreadActualCost>
  <TaskUpdatesResource>1</TaskUpdatesResource>
  <FiscalYearStartMonth>1</FiscalYearStartMonth>
  <CriticalSlackLimit>0</CriticalSlackLimit>
  <Calendars>
    <Calendar>
      <UID>1</UID>
      <Name>BSA_5D_8H_HOL_US</Name>
      <IsBaseCalendar>1</IsBaseCalendar>
      <BaseCalendarUID>-1</BaseCalendarUID>
      <WeekDays>
        <WeekDay>
          <DayType>2</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>3</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>4</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>5</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>6</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>7</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
        <WeekDay>
          <DayType>1</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
      </WeekDays>
      <Exceptions>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-01-01T00:00:00</FromDate>
            <ToDate>2025-01-01T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-01-20T00:00:00</FromDate>
            <ToDate>2025-01-20T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-02-17T00:00:00</FromDate>
            <ToDate>2025-02-17T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-05-26T00:00:00</FromDate>
            <ToDate>2025-05-26T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-06-19T00:00:00</FromDate>
            <ToDate>2025-06-19T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-07-04T00:00:00</FromDate>
            <ToDate>2025-07-04T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-09-01T00:00:00</FromDate>
            <ToDate>2025-09-01T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-10-13T00:00:00</FromDate>
            <ToDate>2025-10-13T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-11-11T00:00:00</FromDate>
            <ToDate>2025-11-11T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-11-27T00:00:00</FromDate>
            <ToDate>2025-11-27T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-12-25T00:00:00</FromDate>
            <ToDate>2025-12-25T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-01-01T00:00:00</FromDate>
            <ToDate>2026-01-01T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-01-19T00:00:00</FromDate>
            <ToDate>2026-01-19T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-02-16T00:00:00</FromDate>
            <ToDate>2026-02-16T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-05-25T00:00:00</FromDate>
            <ToDate>2026-05-25T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-06-19T00:00:00</FromDate>
            <ToDate>2026-06-19T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-07-03T00:00:00</FromDate>
            <ToDate>2026-07-03T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-09-07T00:00:00</FromDate>
            <ToDate>2026-09-07T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-10-12T00:00:00</FromDate>
            <ToDate>2026-10-12T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-11-11T00:00:00</FromDate>
            <ToDate>2026-11-11T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-11-26T00:00:00</FromDate>
            <ToDate>2026-11-26T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-12-25T00:00:00</FromDate>
            <ToDate>2026-12-25T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-01-01T00:00:00</FromDate>
            <ToDate>2027-01-01T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-01-18T00:00:00</FromDate>
            <ToDate>2027-01-18T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-02-15T00:00:00</FromDate>
            <ToDate>2027-02-15T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-05-31T00:00:00</FromDate>
            <ToDate>2027-05-31T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-06-18T00:00:00</FromDate>
            <ToDate>2027-06-18T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-07-05T00:00:00</FromDate>
            <ToDate>2027-07-05T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-09-06T00:00:00</FromDate>
            <ToDate>2027-09-06T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-10-11T00:00:00</FromDate>
            <ToDate>2027-10-11T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-11-11T00:00:00</FromDate>
            <ToDate>2027-11-11T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-11-25T00:00:00</FromDate>
            <ToDate>2027-11-25T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-12-24T00:00:00</FromDate>
            <ToDate>2027-12-24T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-12-31T00:00:00</FromDate>
            <ToDate>2027-12-31T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-01-17T00:00:00</FromDate>
            <ToDate>2028-01-17T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-02-21T00:00:00</FromDate>
            <ToDate>2028-02-21T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-05-29T00:00:00</FromDate>
            <ToDate>2028-05-29T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-06-19T00:00:00</FromDate>
            <ToDate>2028-06-19T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-07-04T00:00:00</FromDate>
            <ToDate>2028-07-04T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-09-04T00:00:00</FromDate>
            <ToDate>2028-09-04T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-10-09T00:00:00</FromDate>
            <ToDate>2028-10-09T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-11-10T00:00:00</FromDate>
            <ToDate>2028-11-10T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-11-23T00:00:00</FromDate>
            <ToDate>2028-11-23T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-12-25T00:00:00</FromDate>
            <ToDate>2028-12-25T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
      </Exceptions>
    </Calendar>
  </Calendars>
  <Tasks>
    <Task>
      <UID>1</UID>
      <ID>1</ID>
      <Name>118,000 SF Tilt-Wall Distribution Warehouse</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>WDH-001</WBS>
      <OutlineNumber/>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-07-20T08:00:00</Start>
      <Finish>2027-06-16T17:00:00</Finish>
      <Duration>PT1832H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>2</UID>
      <ID>2</ID>
      <Name>Milestones</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>WDH-001.MIL</WBS>
      <OutlineNumber/>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-07-20T08:00:00</Start>
      <Finish>2027-06-16T17:00:00</Finish>
      <Duration>PT1832H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>3</UID>
      <ID>3</ID>
      <Name>Notice to Proceed (NTP)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>MIL-00010</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-07-20T08:00:00</Start>
      <Finish>2026-07-20T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>100</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=MLS Disc=PMG Resp=OWN</Notes>
    </Task>
    <Task>
      <UID>4</UID>
      <ID>4</ID>
      <Name>Long-Lead POs Issued</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>MIL-00060</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-07-22T08:00:00</Start>
      <Finish>2026-07-22T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>100</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=MLS Disc=PMG Resp=EPC
Inserted by the BSA milestone standard — consolidated long-lead purchase-order release.</Notes>
      <PredecessorLink>
        <PredecessorUID>14</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>16</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>18</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>5</UID>
      <ID>5</ID>
      <Name>All Long-Lead Equipment On Site</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>MIL-00070</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-14T08:00:00</Start>
      <Finish>2026-12-14T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=MLS Disc=PMG Resp=GC
Rollup of every long-lead delivery — gates Mechanical Completion (BSA standard milestone set).</Notes>
      <PredecessorLink>
        <PredecessorUID>13</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>12</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>20</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>6</UID>
      <ID>6</ID>
      <Name>Mechanical Completion</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>MIL-00020</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-11T08:00:00</Start>
      <Finish>2027-05-11T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=MLS Disc=PMG Resp=OWN</Notes>
      <PredecessorLink>
        <PredecessorUID>5</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>38</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>41</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>40</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>46</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>49</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>7</UID>
      <ID>7</ID>
      <Name>Substantial Completion</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>MIL-00030</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-25T08:00:00</Start>
      <Finish>2027-05-25T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=MLS Disc=PMG Resp=OWN
Target early April 2027 per owner; confirm exact date with owner and AHJ before schedule baseline.</Notes>
      <PredecessorLink>
        <PredecessorUID>52</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>51</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>8</UID>
      <ID>8</ID>
      <Name>Ready for Service</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>MIL-00040</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-06-02T08:00:00</Start>
      <Finish>2027-06-02T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=MLS Disc=PMG Resp=OWN</Notes>
      <PredecessorLink>
        <PredecessorUID>53</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>9</UID>
      <ID>9</ID>
      <Name>Project Closeout</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CLS-00010</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-06-03T08:00:00</Start>
      <Finish>2027-06-16T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CLS Disc=PMG Resp=GC
Project closeout / demobilization — ensures Ready for Service and Final Completion are distinct (BSA standard tail).</Notes>
      <PredecessorLink>
        <PredecessorUID>8</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>10</UID>
      <ID>10</ID>
      <Name>Final Completion</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>MIL-00050</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-06-16T08:00:00</Start>
      <Finish>2027-06-16T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=MLS Disc=PMG Resp=OWN</Notes>
      <PredecessorLink>
        <PredecessorUID>9</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>11</UID>
      <ID>11</ID>
      <Name>Procurement</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>WDH-001.PRO</WBS>
      <OutlineNumber/>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-10-16T08:00:00</Start>
      <Finish>2026-12-14T17:00:00</Finish>
      <Duration>PT320H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>12</UID>
      <ID>12</ID>
      <Name>Dock Equipment On Site</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>PRO-00060</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-10-16T08:00:00</Start>
      <Finish>2026-10-16T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>100</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=PRO Disc=MEC Resp=VND</Notes>
      <PredecessorLink>
        <PredecessorUID>17</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>13</UID>
      <ID>13</ID>
      <Name>Structural Steel Joists &amp; Deck On Site</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>PRO-00030</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-11-06T08:00:00</Start>
      <Finish>2026-11-06T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>100</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=PRO Disc=STR Resp=VND</Notes>
      <PredecessorLink>
        <PredecessorUID>15</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>14</UID>
      <ID>14</ID>
      <Name>Issue PO — Structural Steel Joists &amp; Deck</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>PRO-00010</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-01T08:00:00</Start>
      <Finish>2026-12-01T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>100</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=PRO Disc=STR Resp=GC
15-week lead; PO issued immediately after NTP to protect delivery before panel erection completes.</Notes>
      <PredecessorLink>
        <PredecessorUID>3</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>15</UID>
      <ID>15</ID>
      <Name>Fabricate &amp; Deliver Structural Steel Joists &amp; Deck</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>PRO-00020</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-01T08:00:00</Start>
      <Finish>2026-12-01T17:00:00</Finish>
      <Duration>PT600H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>100</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=PRO Disc=STR Resp=VND
15-week (75 working-day) fabrication and delivery lead time from PO issuance.</Notes>
      <PredecessorLink>
        <PredecessorUID>4</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>16</UID>
      <ID>16</ID>
      <Name>Issue PO — Dock Equipment</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>PRO-00040</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-01T08:00:00</Start>
      <Finish>2026-12-01T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>100</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=PRO Disc=MEC Resp=GC
12-week lead for dock levelers, dock seals, and overhead sectional doors.</Notes>
      <PredecessorLink>
        <PredecessorUID>3</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>17</UID>
      <ID>17</ID>
      <Name>Fabricate &amp; Deliver Dock Equipment</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>PRO-00050</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-01T08:00:00</Start>
      <Finish>2026-12-01T17:00:00</Finish>
      <Duration>PT480H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>100</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=PRO Disc=MEC Resp=VND
12-week (60 working-day) lead time from PO issuance.</Notes>
      <PredecessorLink>
        <PredecessorUID>4</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>18</UID>
      <ID>18</ID>
      <Name>Issue PO — Main Electrical Switchgear</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>PRO-00070</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-01T08:00:00</Start>
      <Finish>2026-12-01T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>100</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=PRO Disc=ELE Resp=GC
20-week lead; switchgear must arrive before interior finishes complete.</Notes>
      <PredecessorLink>
        <PredecessorUID>3</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>19</UID>
      <ID>19</ID>
      <Name>Fabricate &amp; Deliver Main Electrical Switchgear</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>PRO-00080</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-01T08:00:00</Start>
      <Finish>2026-12-14T17:00:00</Finish>
      <Duration>PT800H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>90</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=PRO Disc=ELE Resp=VND
20-week (100 working-day) fabrication and delivery lead time from PO issuance.</Notes>
      <PredecessorLink>
        <PredecessorUID>4</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>20</UID>
      <ID>20</ID>
      <Name>Main Electrical Switchgear On Site</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>PRO-00090</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-14T08:00:00</Start>
      <Finish>2026-12-14T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=PRO Disc=ELE Resp=VND</Notes>
      <PredecessorLink>
        <PredecessorUID>19</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>21</UID>
      <ID>21</ID>
      <Name>Construction</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>WDH-001.CON</WBS>
      <OutlineNumber/>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-01T08:00:00</Start>
      <Finish>2027-05-11T17:00:00</Finish>
      <Duration>PT896H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>22</UID>
      <ID>22</ID>
      <Name>Site &amp; Civil</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>WDH-001.CON.01</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-01T08:00:00</Start>
      <Finish>2026-12-01T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>23</UID>
      <ID>23</ID>
      <Name>Perform Mass Grading &amp; Building Pad</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00010</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-01T08:00:00</Start>
      <Finish>2026-12-01T17:00:00</Finish>
      <Duration>PT200H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>100</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=CIV Resp=GC
Includes rough grading, import/export, subgrade prep, and compaction testing for building pad. Duration assumes 9.2-acre site; confirm soil report.</Notes>
      <PredecessorLink>
        <PredecessorUID>3</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>24</UID>
      <ID>24</ID>
      <Name>Install Site Utilities — Storm &amp; Sanitary</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00020</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-01T08:00:00</Start>
      <Finish>2026-12-01T17:00:00</Finish>
      <Duration>PT160H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>100</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=CIV Resp=SUB
Runs in parallel with spread footings; can begin once grading establishes rough grade in utility corridor.</Notes>
      <PredecessorLink>
        <PredecessorUID>23</PredecessorUID>
        <Type>3</Type>
        <LinkLag>48000</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>25</UID>
      <ID>25</ID>
      <Name>Install Site Utilities — Water &amp; Fire Loop</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00030</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-01T08:00:00</Start>
      <Finish>2026-12-01T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>100</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=CIV Resp=SUB
Fire loop requires utility permit and water purveyor approval; confirm lead time with AHJ.</Notes>
      <PredecessorLink>
        <PredecessorUID>23</PredecessorUID>
        <Type>3</Type>
        <LinkLag>48000</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>26</UID>
      <ID>26</ID>
      <Name>Concrete &amp; Tilt-Wall</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>WDH-001.CON.02</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-01T08:00:00</Start>
      <Finish>2026-12-09T17:00:00</Finish>
      <Duration>PT56H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>27</UID>
      <ID>27</ID>
      <Name>Excavate &amp; Form Spread Footings</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00040</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-01T08:00:00</Start>
      <Finish>2026-12-01T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>100</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=CIV Resp=GC</Notes>
      <PredecessorLink>
        <PredecessorUID>23</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>28</UID>
      <ID>28</ID>
      <Name>Place Concrete Spread Footings</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00050</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-01T08:00:00</Start>
      <Finish>2026-12-01T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>100</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=CIV Resp=GC
Includes embedded anchor bolts and ledger seats for tilt panels.</Notes>
      <PredecessorLink>
        <PredecessorUID>27</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>29</UID>
      <ID>29</ID>
      <Name>Pour Warehouse Floor Slab — Sections 1 &amp; 2 (Casting Bed)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00060</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-01T08:00:00</Start>
      <Finish>2026-12-01T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>100</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=CIV Resp=GC
First slab sections serve as casting bed for tilt-wall panels. Vapor barrier, under-slab plumbing sleeves, and WWF must be placed first.</Notes>
      <PredecessorLink>
        <PredecessorUID>28</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>30</UID>
      <ID>30</ID>
      <Name>Pour Warehouse Floor Slab — Sections 3 &amp; 4</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00070</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-01T08:00:00</Start>
      <Finish>2026-12-01T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>100</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=CIV Resp=GC</Notes>
      <PredecessorLink>
        <PredecessorUID>29</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>31</UID>
      <ID>31</ID>
      <Name>Cast Tilt-Wall Panels (64 Panels)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00080</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-01T08:00:00</Start>
      <Finish>2026-12-01T17:00:00</Finish>
      <Duration>PT160H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>100</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=STR Resp=SUB
Panel casting begins as soon as Sections 1 &amp; 2 slab is ready; roughly 3–4 panels poured per day. Embeds, blockouts, and reveal patterns per engineering drawings.</Notes>
      <PredecessorLink>
        <PredecessorUID>29</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>32</UID>
      <ID>32</ID>
      <Name>Cure Tilt-Wall Panels</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00090</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-01T08:00:00</Start>
      <Finish>2026-12-09T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>35</PercentComplete>
      <RemainingDuration>PT52H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=STR Resp=SUB
10-working-day cure period modeled as explicit activity; no long lags. Bond breaker applied prior to pour.</Notes>
      <PredecessorLink>
        <PredecessorUID>31</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>33</UID>
      <ID>33</ID>
      <Name>Structure &amp; Envelope</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>WDH-001.CON.03</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-10T08:00:00</Start>
      <Finish>2027-02-23T17:00:00</Finish>
      <Duration>PT400H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>34</UID>
      <ID>34</ID>
      <Name>Erect Tilt-Wall Panels with Mobile Crane</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00100</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-10T08:00:00</Start>
      <Finish>2026-12-31T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT120H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=STR Resp=SUB
3-week panel erection; crane access requires clear truck court. Temporary bracing remains until steel joists are set.</Notes>
      <PredecessorLink>
        <PredecessorUID>32</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>35</UID>
      <ID>35</ID>
      <Name>Erect Structural Steel Joists &amp; Roof Deck</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00110</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-25T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT120H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=STR Resp=SUB
Erection begins immediately after panels are up. Steel must be on site (PRO-00030) before erection can start.</Notes>
      <PredecessorLink>
        <PredecessorUID>34</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>13</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>36</UID>
      <ID>36</ID>
      <Name>Install TPO Roofing &amp; Insulation</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00120</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-26T08:00:00</Start>
      <Finish>2027-02-23T17:00:00</Finish>
      <Duration>PT160H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT160H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=ARC Resp=SUB
TPO installation dries in the building, enabling interior work to proceed. Confirm R-value and membrane thickness with architect.</Notes>
      <PredecessorLink>
        <PredecessorUID>35</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>37</UID>
      <ID>37</ID>
      <Name>Warehouse Interior</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>WDH-001.CON.04</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-24T08:00:00</Start>
      <Finish>2027-04-06T17:00:00</Finish>
      <Duration>PT240H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>38</UID>
      <ID>38</ID>
      <Name>Install ESFR Fire Sprinkler System</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00130</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-24T08:00:00</Start>
      <Finish>2027-03-30T17:00:00</Finish>
      <Duration>PT200H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT200H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=MEC Resp=SUB
ESFR system; requires building dry-in and fire loop water service. Coordinate with fire marshal for hydraulic calc approval.</Notes>
      <PredecessorLink>
        <PredecessorUID>36</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>39</UID>
      <ID>39</ID>
      <Name>Install Warehouse Electrical &amp; Lighting</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00140</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-24T08:00:00</Start>
      <Finish>2027-03-30T17:00:00</Finish>
      <Duration>PT200H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT200H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=ELE Resp=SUB
Rough-in and fixture installation; LED high-bay lighting. Runs concurrent with ESFR and dock equipment installation.</Notes>
      <PredecessorLink>
        <PredecessorUID>36</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>40</UID>
      <ID>40</ID>
      <Name>Install Dock Equipment &amp; Overhead Doors</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00160</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-24T08:00:00</Start>
      <Finish>2027-03-09T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=MEC Resp=SUB
Dock levelers, dock seals, and sectional doors. Equipment must be on site (PRO-00060).</Notes>
      <PredecessorLink>
        <PredecessorUID>12</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>36</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>41</UID>
      <ID>41</ID>
      <Name>Set &amp; Energize Main Electrical Switchgear</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00150</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-31T08:00:00</Start>
      <Finish>2027-04-06T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT40H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=ELE Resp=SUB
Switchgear must be on site (PRO-00090) and warehouse electrical rough-in substantially complete before setting. Utility company coordination required for energization.</Notes>
      <PredecessorLink>
        <PredecessorUID>39</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>20</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>42</UID>
      <ID>42</ID>
      <Name>Office Buildout</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>WDH-001.CON.05</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-24T08:00:00</Start>
      <Finish>2027-05-11T17:00:00</Finish>
      <Duration>PT440H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>43</UID>
      <ID>43</ID>
      <Name>Frame Metal Stud Walls — Office</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00170</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-24T08:00:00</Start>
      <Finish>2027-03-09T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=STR Resp=SUB</Notes>
      <PredecessorLink>
        <PredecessorUID>36</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>30</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>44</UID>
      <ID>44</ID>
      <Name>Rough-In MEP — Office</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00180</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-10T08:00:00</Start>
      <Finish>2027-03-30T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT120H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=EIN Resp=SUB
Electrical, mechanical, and plumbing rough-ins for 6,500 SF two-story office. Coordinate MEP above ceiling with structural.</Notes>
      <PredecessorLink>
        <PredecessorUID>43</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>45</UID>
      <ID>45</ID>
      <Name>Install Drywall, Ceilings &amp; Insulation — Office</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00190</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-31T08:00:00</Start>
      <Finish>2027-04-20T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT120H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=ARC Resp=SUB</Notes>
      <PredecessorLink>
        <PredecessorUID>44</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>46</UID>
      <ID>46</ID>
      <Name>Install Finishes &amp; Storefront Glazing — Office</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00200</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-21T08:00:00</Start>
      <Finish>2027-05-11T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT120H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=ARC Resp=SUB
Includes paint, flooring, millwork, storefront aluminum and glazing. Storefront glazing vendor lead time should be confirmed.</Notes>
      <PredecessorLink>
        <PredecessorUID>45</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>47</UID>
      <ID>47</ID>
      <Name>Site Completion</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>WDH-001.CON.06</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-02-08T17:00:00</Finish>
      <Duration>PT200H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>48</UID>
      <ID>48</ID>
      <Name>Pave Car Court &amp; Truck Court</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00210</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-04T08:00:00</Start>
      <Finish>2027-01-25T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT120H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=CIV Resp=SUB
After panel erection and crane demobilization; aggregate base and concrete or asphalt paving. Confirm paving section with geotech.</Notes>
      <PredecessorLink>
        <PredecessorUID>34</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>24</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>25</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>49</UID>
      <ID>49</ID>
      <Name>Install Landscaping &amp; Irrigation</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00220</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-26T08:00:00</Start>
      <Finish>2027-02-08T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=CIV Resp=SUB
Late-job scope after hardscape is complete. Confirm plant palette and irrigation design with civil/landscape architect.</Notes>
      <PredecessorLink>
        <PredecessorUID>48</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>50</UID>
      <ID>50</ID>
      <Name>Commissioning &amp; Closeout</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>WDH-001.COM</WBS>
      <OutlineNumber/>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-12T08:00:00</Start>
      <Finish>2027-06-02T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>51</UID>
      <ID>51</ID>
      <Name>Perform Commissioning &amp; Start-Up</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>COM-00010</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-12T08:00:00</Start>
      <Finish>2027-05-25T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=COM Disc=PMG Resp=GC
Includes pre-commissioning checks, MEP systems start-up, fire sprinkler system acceptance test, and electrical point-to-point verification. Open end — no successor; auto-wired to Substantial Completion — review.</Notes>
      <PredecessorLink>
        <PredecessorUID>38</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>41</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>40</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>46</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>49</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>6</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>52</UID>
      <ID>52</ID>
      <Name>Complete Punchlist &amp; Final Inspections</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>COM-00020</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-12T08:00:00</Start>
      <Finish>2027-05-25T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CLS Disc=PMG Resp=GC
Certificate of occupancy inspection, AHJ final, and owner punchlist completion. Approximately 3 weeks combined with commissioning.</Notes>
      <PredecessorLink>
        <PredecessorUID>6</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>53</UID>
      <ID>53</ID>
      <Name>Execute Project Closeout</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>COM-00030</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-26T08:00:00</Start>
      <Finish>2027-06-02T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT40H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CLS Disc=PMG Resp=GC
As-built drawings, O&amp;M manuals, warranty letters, and lien releases.</Notes>
      <PredecessorLink>
        <PredecessorUID>7</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
  </Tasks>
</Project>