<?xml version="1.0" encoding="UTF-8"?>
<Project xmlns="http://schemas.microsoft.com/project">
  <SaveVersion>14</SaveVersion>
  <Name>Custom Single-Family Residence — Texas Hill Country</Name>
  <Title>Custom Single-Family Residence — Texas Hill Country</Title>
  <Author>Big State AI (BSA)</Author>
  <ScheduleFromStart>1</ScheduleFromStart>
  <StartDate>2026-08-10T08:00:00</StartDate>
  <FinishDate>2027-02-05T17:00:00</FinishDate>
  <CalendarUID>1</CalendarUID>
  <DefaultStartTime>08:00:00</DefaultStartTime>
  <DefaultFinishTime>17:00:00</DefaultFinishTime>
  <MinutesPerDay>480</MinutesPerDay>
  <MinutesPerWeek>2400</MinutesPerWeek>
  <DaysPerMonth>20</DaysPerMonth>
  <DefaultTaskType>1</DefaultTaskType>
  <DefaultFixedCostAccrual>3</DefaultFixedCostAccrual>
  <NewTasksEffortDriven>0</NewTasksEffortDriven>
  <NewTasksAreManual>0</NewTasksAreManual>
  <SpreadActualCost>0</SpreadActualCost>
  <TaskUpdatesResource>1</TaskUpdatesResource>
  <FiscalYearStartMonth>1</FiscalYearStartMonth>
  <CriticalSlackLimit>0</CriticalSlackLimit>
  <Calendars>
    <Calendar>
      <UID>1</UID>
      <Name>BSA_5D_8H_HOL_US</Name>
      <IsBaseCalendar>1</IsBaseCalendar>
      <BaseCalendarUID>-1</BaseCalendarUID>
      <WeekDays>
        <WeekDay>
          <DayType>2</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>3</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>4</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>5</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>6</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>7</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
        <WeekDay>
          <DayType>1</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
      </WeekDays>
      <Exceptions>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-01-01T00:00:00</FromDate>
            <ToDate>2025-01-01T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-01-20T00:00:00</FromDate>
            <ToDate>2025-01-20T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-02-17T00:00:00</FromDate>
            <ToDate>2025-02-17T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-05-26T00:00:00</FromDate>
            <ToDate>2025-05-26T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-06-19T00:00:00</FromDate>
            <ToDate>2025-06-19T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-07-04T00:00:00</FromDate>
            <ToDate>2025-07-04T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-09-01T00:00:00</FromDate>
            <ToDate>2025-09-01T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-10-13T00:00:00</FromDate>
            <ToDate>2025-10-13T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-11-11T00:00:00</FromDate>
            <ToDate>2025-11-11T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-11-27T00:00:00</FromDate>
            <ToDate>2025-11-27T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-12-25T00:00:00</FromDate>
            <ToDate>2025-12-25T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-01-01T00:00:00</FromDate>
            <ToDate>2026-01-01T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-01-19T00:00:00</FromDate>
            <ToDate>2026-01-19T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-02-16T00:00:00</FromDate>
            <ToDate>2026-02-16T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-05-25T00:00:00</FromDate>
            <ToDate>2026-05-25T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-06-19T00:00:00</FromDate>
            <ToDate>2026-06-19T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-07-03T00:00:00</FromDate>
            <ToDate>2026-07-03T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-09-07T00:00:00</FromDate>
            <ToDate>2026-09-07T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-10-12T00:00:00</FromDate>
            <ToDate>2026-10-12T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-11-11T00:00:00</FromDate>
            <ToDate>2026-11-11T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-11-26T00:00:00</FromDate>
            <ToDate>2026-11-26T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-12-25T00:00:00</FromDate>
            <ToDate>2026-12-25T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-01-01T00:00:00</FromDate>
            <ToDate>2027-01-01T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-01-18T00:00:00</FromDate>
            <ToDate>2027-01-18T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-02-15T00:00:00</FromDate>
            <ToDate>2027-02-15T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-05-31T00:00:00</FromDate>
            <ToDate>2027-05-31T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-06-18T00:00:00</FromDate>
            <ToDate>2027-06-18T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-07-05T00:00:00</FromDate>
            <ToDate>2027-07-05T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-09-06T00:00:00</FromDate>
            <ToDate>2027-09-06T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-10-11T00:00:00</FromDate>
            <ToDate>2027-10-11T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-11-11T00:00:00</FromDate>
            <ToDate>2027-11-11T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-11-25T00:00:00</FromDate>
            <ToDate>2027-11-25T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-12-24T00:00:00</FromDate>
            <ToDate>2027-12-24T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-12-31T00:00:00</FromDate>
            <ToDate>2027-12-31T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-01-17T00:00:00</FromDate>
            <ToDate>2028-01-17T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-02-21T00:00:00</FromDate>
            <ToDate>2028-02-21T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-05-29T00:00:00</FromDate>
            <ToDate>2028-05-29T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-06-19T00:00:00</FromDate>
            <ToDate>2028-06-19T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-07-04T00:00:00</FromDate>
            <ToDate>2028-07-04T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-09-04T00:00:00</FromDate>
            <ToDate>2028-09-04T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-10-09T00:00:00</FromDate>
            <ToDate>2028-10-09T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-11-10T00:00:00</FromDate>
            <ToDate>2028-11-10T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-11-23T00:00:00</FromDate>
            <ToDate>2028-11-23T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-12-25T00:00:00</FromDate>
            <ToDate>2028-12-25T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
      </Exceptions>
    </Calendar>
  </Calendars>
  <Tasks>
    <Task>
      <UID>1</UID>
      <ID>1</ID>
      <Name>Custom Single-Family Residence — Texas Hill Country</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>TRM-001</WBS>
      <OutlineNumber/>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-08-10T08:00:00</Start>
      <Finish>2027-02-05T17:00:00</Finish>
      <Duration>PT984H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>2</UID>
      <ID>2</ID>
      <Name>Milestones</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>TRM-001.MIL</WBS>
      <OutlineNumber/>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-08-10T08:00:00</Start>
      <Finish>2027-02-05T17:00:00</Finish>
      <Duration>PT984H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>3</UID>
      <ID>3</ID>
      <Name>Notice to Proceed</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>MIL-00010</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-08-10T08:00:00</Start>
      <Finish>2026-08-10T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=MLS Disc=PMG Resp=OWN
Building permit already in hand. NTP anchors to 2026-08-10 per project directive; all work flows forward via CPM from this milestone.</Notes>
    </Task>
    <Task>
      <UID>4</UID>
      <ID>4</ID>
      <Name>Foundation Complete</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>MIL-00020</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-09-28T08:00:00</Start>
      <Finish>2026-09-28T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=MLS Disc=PMG Resp=OWN</Notes>
      <PredecessorLink>
        <PredecessorUID>16</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>5</UID>
      <ID>5</ID>
      <Name>Framing Complete</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>MIL-00030</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-10-27T08:00:00</Start>
      <Finish>2026-10-27T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=MLS Disc=PMG Resp=OWN</Notes>
      <PredecessorLink>
        <PredecessorUID>20</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>6</UID>
      <ID>6</ID>
      <Name>Dry-In / Weather-Tight</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>MIL-00040</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-10-27T08:00:00</Start>
      <Finish>2026-10-27T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=MLS Disc=PMG Resp=OWN
House dried-in once metal roof and all windows/exterior doors are installed, targeting mid-November 2026 per narrative.</Notes>
      <PredecessorLink>
        <PredecessorUID>21</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>5</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>7</UID>
      <ID>7</ID>
      <Name>Frame Inspection Passed</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>MIL-00050</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-10-28T08:00:00</Start>
      <Finish>2026-10-28T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=MLS Disc=PMG Resp=OWN
City frame inspection gates insulation and drywall start. Allow 1-day inspection activity; milestone fires on pass.</Notes>
      <PredecessorLink>
        <PredecessorUID>23</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>8</UID>
      <ID>8</ID>
      <Name>Certificate of Occupancy</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>MIL-00060</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-03T08:00:00</Start>
      <Finish>2027-02-03T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=MLS Disc=PMG Resp=OWN
CO targeted late January 2027 per owner/builder; schedule logic drives the date — no hard constraint set.</Notes>
      <PredecessorLink>
        <PredecessorUID>42</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>9</UID>
      <ID>9</ID>
      <Name>Final Completion / Owner Closeout</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>MIL-00070</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-05T08:00:00</Start>
      <Finish>2027-02-05T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=MLS Disc=PMG Resp=OWN</Notes>
      <PredecessorLink>
        <PredecessorUID>43</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>10</UID>
      <ID>10</ID>
      <Name>Construction</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>TRM-001.CON</WBS>
      <OutlineNumber/>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-08-10T08:00:00</Start>
      <Finish>2027-01-29T17:00:00</Finish>
      <Duration>PT944H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>11</UID>
      <ID>11</ID>
      <Name>Site Work &amp; Foundation</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>TRM-001.CON.01</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-08-10T08:00:00</Start>
      <Finish>2026-09-28T17:00:00</Finish>
      <Duration>PT280H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>12</UID>
      <ID>12</ID>
      <Name>Clear Site and Strip Topsoil</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00010</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-08-10T08:00:00</Start>
      <Finish>2026-08-14T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT40H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=CIV Resp=GC
Approximately 1 week per narrative. Includes clearing native cedar/brush typical of Hill Country sites.</Notes>
      <PredecessorLink>
        <PredecessorUID>3</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>13</UID>
      <ID>13</ID>
      <Name>Grade and Compact Building Pad</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00020</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-08-17T08:00:00</Start>
      <Finish>2026-08-21T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT40H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=CIV Resp=GC
Building pad included in the 1-week site work duration; modeled as a successor to clearing to show sequence. Combined with clearing = ~1 week total; split for visibility.</Notes>
      <PredecessorLink>
        <PredecessorUID>12</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>14</UID>
      <ID>14</ID>
      <Name>Set Slab Forms and Lay Under-Slab Plumbing</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00030</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-08-24T08:00:00</Start>
      <Finish>2026-09-04T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=CIV Resp=GC
Under-slab plumbing rough-in by plumbing sub concurrent with form-setting; ~2 weeks combined per narrative.</Notes>
      <PredecessorLink>
        <PredecessorUID>13</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>15</UID>
      <ID>15</ID>
      <Name>Install Post-Tensioned Reinforcing and Pour Slab</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00040</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-09-08T08:00:00</Start>
      <Finish>2026-09-21T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=STR Resp=GC
PT reinforcing placed then slab poured; ~2 weeks. Tendons stressed approximately 7–10 days after pour before framing begins.</Notes>
      <PredecessorLink>
        <PredecessorUID>14</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>16</UID>
      <ID>16</ID>
      <Name>Stress Post-Tensioned Tendons</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00050</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-09-22T08:00:00</Start>
      <Finish>2026-09-28T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT40H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=STR Resp=SUB
PT stressing crew returns ~7 days after pour once concrete reaches design strength. 1-week activity covers mobilization, stressing, and tail cut.</Notes>
      <PredecessorLink>
        <PredecessorUID>15</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>17</UID>
      <ID>17</ID>
      <Name>Framing &amp; Envelope</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>TRM-001.CON.02</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-09-29T08:00:00</Start>
      <Finish>2026-10-27T17:00:00</Finish>
      <Duration>PT160H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>18</UID>
      <ID>18</ID>
      <Name>Frame Exterior and Interior Walls</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00060</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-09-29T08:00:00</Start>
      <Finish>2026-10-13T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=STR Resp=GC
3-week framing scope split into walls (2 wks) and roof framing (1 wk) for schedule visibility. Experienced crew per narrative.</Notes>
      <PredecessorLink>
        <PredecessorUID>4</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>19</UID>
      <ID>19</ID>
      <Name>Frame Roof Structure and Sheathing</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00070</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-10-14T08:00:00</Start>
      <Finish>2026-10-20T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT40H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=STR Resp=GC</Notes>
      <PredecessorLink>
        <PredecessorUID>18</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>20</UID>
      <ID>20</ID>
      <Name>Install Standing-Seam Metal Roof</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00080</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-10-21T08:00:00</Start>
      <Finish>2026-10-27T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT40H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=ARC Resp=SUB
~1 week per narrative. Specialty subcontractor for standing-seam metal in Hill Country.</Notes>
      <PredecessorLink>
        <PredecessorUID>19</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>21</UID>
      <ID>21</ID>
      <Name>Install Windows and Exterior Doors</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00090</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-10-21T08:00:00</Start>
      <Finish>2026-10-23T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT24H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=ARC Resp=SUB
~3 days per narrative. Windows and doors delivered to site before install; builder to confirm lead time and pre-order accordingly.</Notes>
      <PredecessorLink>
        <PredecessorUID>19</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>22</UID>
      <ID>22</ID>
      <Name>Rough-In &amp; Insulation</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>TRM-001.CON.03</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-10-28T08:00:00</Start>
      <Finish>2026-11-12T17:00:00</Finish>
      <Duration>PT88H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>23</UID>
      <ID>23</ID>
      <Name>Perform Frame Inspection</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00100</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-10-28T08:00:00</Start>
      <Finish>2026-10-28T17:00:00</Finish>
      <Duration>PT8H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT8H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=PMG Resp=OWN
City inspection activity. Milestone MIL-00050 fires on completion/pass. If failed, re-inspection adds float consumption — flag as risk.</Notes>
      <PredecessorLink>
        <PredecessorUID>6</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>24</UID>
      <ID>24</ID>
      <Name>Install Rough Mechanical (HVAC)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00110</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-10-29T08:00:00</Start>
      <Finish>2026-11-12T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=MEC Resp=SUB
~2 weeks concurrent with electrical and plumbing rough-ins per narrative.</Notes>
      <PredecessorLink>
        <PredecessorUID>7</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>25</UID>
      <ID>25</ID>
      <Name>Install Rough Electrical</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00120</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-10-29T08:00:00</Start>
      <Finish>2026-11-12T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=ELE Resp=SUB
~2 weeks concurrent with MEP rough-ins. Must follow frame inspection pass.</Notes>
      <PredecessorLink>
        <PredecessorUID>7</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>26</UID>
      <ID>26</ID>
      <Name>Install Rough Plumbing (Above Slab)</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00130</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-10-29T08:00:00</Start>
      <Finish>2026-11-12T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=MEC Resp=SUB
~2 weeks concurrent with MEP rough-ins. Must follow frame inspection pass.</Notes>
      <PredecessorLink>
        <PredecessorUID>7</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>27</UID>
      <ID>27</ID>
      <Name>Drywall &amp; Interior Finishes</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>TRM-001.CON.04</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-11-13T08:00:00</Start>
      <Finish>2027-01-29T17:00:00</Finish>
      <Duration>PT416H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>28</UID>
      <ID>28</ID>
      <Name>Apply Spray-Foam Insulation</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00140</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-11-13T08:00:00</Start>
      <Finish>2026-11-17T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT24H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=ARC Resp=SUB
~3 days per narrative. Must follow all rough-in trades to avoid having to cut insulation for re-work.</Notes>
      <PredecessorLink>
        <PredecessorUID>24</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>25</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>26</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>29</UID>
      <ID>29</ID>
      <Name>Hang and Finish Drywall</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00150</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-11-18T08:00:00</Start>
      <Finish>2026-12-02T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=ARC Resp=SUB
~2 weeks per narrative.</Notes>
      <PredecessorLink>
        <PredecessorUID>28</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>30</UID>
      <ID>30</ID>
      <Name>Install Cabinets and Countertops</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00160</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-03T08:00:00</Start>
      <Finish>2026-12-16T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=ARC Resp=SUB
Interior finishes overlap ~6 weeks total. Cabinets/countertops lead; countertop template after cabinet install, then fabrication turnaround ~2 weeks — builder to track as potential float consumer.</Notes>
      <PredecessorLink>
        <PredecessorUID>29</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>31</UID>
      <ID>31</ID>
      <Name>Install Tile and Stone Finishes</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00170</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-03T08:00:00</Start>
      <Finish>2026-12-16T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=ARC Resp=SUB
Runs concurrent with cabinet/countertop scope in separate areas of house.</Notes>
      <PredecessorLink>
        <PredecessorUID>29</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>32</UID>
      <ID>32</ID>
      <Name>Install Trim Carpentry and Interior Doors</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00180</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-17T08:00:00</Start>
      <Finish>2026-12-28T17:00:00</Finish>
      <Duration>PT56H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT56H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=ARC Resp=SUB</Notes>
      <PredecessorLink>
        <PredecessorUID>30</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>31</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>33</UID>
      <ID>33</ID>
      <Name>Paint Interior and Exterior Primer/Finish</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00190</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-29T08:00:00</Start>
      <Finish>2027-01-12T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=ARC Resp=SUB
Paint follows trim; overlaps with flooring in sequenced areas.</Notes>
      <PredecessorLink>
        <PredecessorUID>32</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>34</UID>
      <ID>34</ID>
      <Name>Install Wood Flooring</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00200</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-13T08:00:00</Start>
      <Finish>2027-01-22T17:00:00</Finish>
      <Duration>PT56H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT56H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=ARC Resp=SUB
Flooring near-last interior finish to avoid damage from other trades.</Notes>
      <PredecessorLink>
        <PredecessorUID>33</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>35</UID>
      <ID>35</ID>
      <Name>Complete MEP Trim-Out and Fixture Installation</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00210</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-25T08:00:00</Start>
      <Finish>2027-01-29T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT40H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=MEC Resp=SUB
~1 week per narrative. Includes HVAC equipment final connections, plumbing fixtures, electrical devices/fixtures, and panel trim. Follows flooring and paint.</Notes>
      <PredecessorLink>
        <PredecessorUID>34</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>36</UID>
      <ID>36</ID>
      <Name>Exterior Finishes &amp; Site</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>TRM-001.CON.05</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-10-28T08:00:00</Start>
      <Finish>2026-11-30T17:00:00</Finish>
      <Duration>PT176H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>37</UID>
      <ID>37</ID>
      <Name>Install Limestone Masonry Exterior</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00220</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-10-28T08:00:00</Start>
      <Finish>2026-11-18T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT120H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=STR Resp=SUB
Limestone veneer on exterior; runs parallel with interior finishes per narrative. Hill Country limestone — confirm material availability and mason crew lead time.</Notes>
      <PredecessorLink>
        <PredecessorUID>6</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>38</UID>
      <ID>38</ID>
      <Name>Pour Driveway and Flatwork Concrete</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00240</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-10-28T08:00:00</Start>
      <Finish>2026-11-03T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT40H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=CIV Resp=GC
Driveway and exterior flatwork; runs parallel with interior finishes. Sequence after rough exterior grading is complete.</Notes>
      <PredecessorLink>
        <PredecessorUID>6</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>39</UID>
      <ID>39</ID>
      <Name>Final Grade, Landscaping, and Irrigation</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00250</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-11-04T08:00:00</Start>
      <Finish>2026-11-13T17:00:00</Finish>
      <Duration>PT56H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT56H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=CIV Resp=SUB
Final grading, sod/native plantings, and irrigation system per narrative. Runs parallel with late interior finishes.</Notes>
      <PredecessorLink>
        <PredecessorUID>38</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>40</UID>
      <ID>40</ID>
      <Name>Apply Stucco Exterior Finish</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00230</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-11-19T08:00:00</Start>
      <Finish>2026-11-30T17:00:00</Finish>
      <Duration>PT56H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT56H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=ARC Resp=SUB
Stucco on non-limestone elevations; follows limestone on those elevations. 3-coat system typical — allow cure time between coats included in duration.</Notes>
      <PredecessorLink>
        <PredecessorUID>37</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>41</UID>
      <ID>41</ID>
      <Name>Closeout</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>TRM-001.CLS</WBS>
      <OutlineNumber/>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-01T08:00:00</Start>
      <Finish>2027-02-05T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>42</UID>
      <ID>42</ID>
      <Name>Conduct Punch List and Final Inspections</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00260</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-01T08:00:00</Start>
      <Finish>2027-02-03T17:00:00</Finish>
      <Duration>PT24H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT24H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CLS Disc=PMG Resp=GC
~1 week combined per narrative; split into punch list/inspections (3 days) and owner walkthrough (2 days) for clarity.</Notes>
      <PredecessorLink>
        <PredecessorUID>35</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>40</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>39</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>43</UID>
      <ID>43</ID>
      <Name>Conduct Owner Walkthrough and Deliver Home</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00270</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-04T08:00:00</Start>
      <Finish>2027-02-05T17:00:00</Finish>
      <Duration>PT16H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT16H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CLS Disc=PMG Resp=OWN</Notes>
      <PredecessorLink>
        <PredecessorUID>8</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
  </Tasks>
</Project>