<?xml version="1.0" encoding="UTF-8"?>
<Project xmlns="http://schemas.microsoft.com/project">
  <SaveVersion>14</SaveVersion>
  <Name>FM 2350 Potable Water Booster Pump Station</Name>
  <Title>FM 2350 Potable Water Booster Pump Station</Title>
  <Author>Big State AI (BSA)</Author>
  <ScheduleFromStart>1</ScheduleFromStart>
  <StartDate>2026-08-17T08:00:00</StartDate>
  <FinishDate>2027-06-17T17:00:00</FinishDate>
  <CalendarUID>1</CalendarUID>
  <DefaultStartTime>08:00:00</DefaultStartTime>
  <DefaultFinishTime>17:00:00</DefaultFinishTime>
  <MinutesPerDay>480</MinutesPerDay>
  <MinutesPerWeek>2400</MinutesPerWeek>
  <DaysPerMonth>20</DaysPerMonth>
  <DefaultTaskType>1</DefaultTaskType>
  <DefaultFixedCostAccrual>3</DefaultFixedCostAccrual>
  <NewTasksEffortDriven>0</NewTasksEffortDriven>
  <NewTasksAreManual>0</NewTasksAreManual>
  <SpreadActualCost>0</SpreadActualCost>
  <TaskUpdatesResource>1</TaskUpdatesResource>
  <FiscalYearStartMonth>1</FiscalYearStartMonth>
  <CriticalSlackLimit>0</CriticalSlackLimit>
  <Calendars>
    <Calendar>
      <UID>1</UID>
      <Name>BSA_5D_8H_HOL_US</Name>
      <IsBaseCalendar>1</IsBaseCalendar>
      <BaseCalendarUID>-1</BaseCalendarUID>
      <WeekDays>
        <WeekDay>
          <DayType>2</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>3</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>4</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>5</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>6</DayType>
          <DayWorking>1</DayWorking>
          <WorkingTimes>
            <WorkingTime>
              <FromTime>08:00:00</FromTime>
              <ToTime>12:00:00</ToTime>
            </WorkingTime>
            <WorkingTime>
              <FromTime>13:00:00</FromTime>
              <ToTime>17:00:00</ToTime>
            </WorkingTime>
          </WorkingTimes>
        </WeekDay>
        <WeekDay>
          <DayType>7</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
        <WeekDay>
          <DayType>1</DayType>
          <DayWorking>0</DayWorking>
        </WeekDay>
      </WeekDays>
      <Exceptions>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-01-01T00:00:00</FromDate>
            <ToDate>2025-01-01T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-01-20T00:00:00</FromDate>
            <ToDate>2025-01-20T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-02-17T00:00:00</FromDate>
            <ToDate>2025-02-17T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-05-26T00:00:00</FromDate>
            <ToDate>2025-05-26T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-06-19T00:00:00</FromDate>
            <ToDate>2025-06-19T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-07-04T00:00:00</FromDate>
            <ToDate>2025-07-04T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-09-01T00:00:00</FromDate>
            <ToDate>2025-09-01T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-10-13T00:00:00</FromDate>
            <ToDate>2025-10-13T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-11-11T00:00:00</FromDate>
            <ToDate>2025-11-11T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-11-27T00:00:00</FromDate>
            <ToDate>2025-11-27T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2025-12-25T00:00:00</FromDate>
            <ToDate>2025-12-25T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-01-01T00:00:00</FromDate>
            <ToDate>2026-01-01T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-01-19T00:00:00</FromDate>
            <ToDate>2026-01-19T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-02-16T00:00:00</FromDate>
            <ToDate>2026-02-16T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-05-25T00:00:00</FromDate>
            <ToDate>2026-05-25T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-06-19T00:00:00</FromDate>
            <ToDate>2026-06-19T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-07-03T00:00:00</FromDate>
            <ToDate>2026-07-03T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-09-07T00:00:00</FromDate>
            <ToDate>2026-09-07T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-10-12T00:00:00</FromDate>
            <ToDate>2026-10-12T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-11-11T00:00:00</FromDate>
            <ToDate>2026-11-11T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-11-26T00:00:00</FromDate>
            <ToDate>2026-11-26T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2026-12-25T00:00:00</FromDate>
            <ToDate>2026-12-25T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-01-01T00:00:00</FromDate>
            <ToDate>2027-01-01T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-01-18T00:00:00</FromDate>
            <ToDate>2027-01-18T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-02-15T00:00:00</FromDate>
            <ToDate>2027-02-15T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-05-31T00:00:00</FromDate>
            <ToDate>2027-05-31T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-06-18T00:00:00</FromDate>
            <ToDate>2027-06-18T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-07-05T00:00:00</FromDate>
            <ToDate>2027-07-05T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-09-06T00:00:00</FromDate>
            <ToDate>2027-09-06T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-10-11T00:00:00</FromDate>
            <ToDate>2027-10-11T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-11-11T00:00:00</FromDate>
            <ToDate>2027-11-11T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-11-25T00:00:00</FromDate>
            <ToDate>2027-11-25T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-12-24T00:00:00</FromDate>
            <ToDate>2027-12-24T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2027-12-31T00:00:00</FromDate>
            <ToDate>2027-12-31T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-01-17T00:00:00</FromDate>
            <ToDate>2028-01-17T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-02-21T00:00:00</FromDate>
            <ToDate>2028-02-21T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-05-29T00:00:00</FromDate>
            <ToDate>2028-05-29T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-06-19T00:00:00</FromDate>
            <ToDate>2028-06-19T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-07-04T00:00:00</FromDate>
            <ToDate>2028-07-04T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-09-04T00:00:00</FromDate>
            <ToDate>2028-09-04T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-10-09T00:00:00</FromDate>
            <ToDate>2028-10-09T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-11-10T00:00:00</FromDate>
            <ToDate>2028-11-10T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-11-23T00:00:00</FromDate>
            <ToDate>2028-11-23T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
        <Exception>
          <EnteredByOccurrences>0</EnteredByOccurrences>
          <TimePeriod>
            <FromDate>2028-12-25T00:00:00</FromDate>
            <ToDate>2028-12-25T23:59:00</ToDate>
          </TimePeriod>
          <Occurrences>1</Occurrences>
          <Name>Holiday</Name>
          <Type>1</Type>
          <DayWorking>0</DayWorking>
        </Exception>
      </Exceptions>
    </Calendar>
  </Calendars>
  <Tasks>
    <Task>
      <UID>1</UID>
      <ID>1</ID>
      <Name>FM 2350 Potable Water Booster Pump Station</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>WBS-001</WBS>
      <OutlineNumber/>
      <OutlineLevel>1</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-08-17T08:00:00</Start>
      <Finish>2027-06-17T17:00:00</Finish>
      <Duration>PT1680H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>2</UID>
      <ID>2</ID>
      <Name>Milestones</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>WBS-001.MIL</WBS>
      <OutlineNumber/>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-08-17T08:00:00</Start>
      <Finish>2027-06-17T17:00:00</Finish>
      <Duration>PT1680H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>3</UID>
      <ID>3</ID>
      <Name>Notice to Proceed</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>MIL-00010</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-08-17T08:00:00</Start>
      <Finish>2026-08-17T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=MLS Disc=PMG Resp=OWN</Notes>
    </Task>
    <Task>
      <UID>4</UID>
      <ID>4</ID>
      <Name>Long-Lead POs Issued</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>MIL-00090</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-08-17T08:00:00</Start>
      <Finish>2026-08-17T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=MLS Disc=PMG Resp=EPC
Inserted by the BSA milestone standard — consolidated long-lead purchase-order release.</Notes>
      <PredecessorLink>
        <PredecessorUID>3</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>5</UID>
      <ID>5</ID>
      <Name>All Long-Lead Equipment On Site</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>MIL-00100</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-03T08:00:00</Start>
      <Finish>2027-03-03T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=MLS Disc=PMG Resp=GC
Rollup of every long-lead delivery — gates Mechanical Completion (BSA standard milestone set).</Notes>
      <PredecessorLink>
        <PredecessorUID>16</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>17</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>18</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>6</UID>
      <ID>6</ID>
      <Name>Mechanical Completion</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>MIL-00050</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-14T08:00:00</Start>
      <Finish>2027-04-14T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=MLS Disc=PMG Resp=OWN</Notes>
      <PredecessorLink>
        <PredecessorUID>24</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>23</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>5</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>28</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>37</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>42</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>43</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>7</UID>
      <ID>7</ID>
      <Name>Substantial Completion</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>MIL-00060</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-12T08:00:00</Start>
      <Finish>2027-05-12T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=MLS Disc=PMG Resp=OWN
Target June 2027; duration-driven by CPM — no hard constraint set.</Notes>
      <PredecessorLink>
        <PredecessorUID>6</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>49</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>8</UID>
      <ID>8</ID>
      <Name>Ready for Service</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>MIL-00070</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-06-03T08:00:00</Start>
      <Finish>2027-06-03T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=MLS Disc=PMG Resp=OWN</Notes>
      <PredecessorLink>
        <PredecessorUID>50</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>9</UID>
      <ID>9</ID>
      <Name>Project Closeout</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CLS-00010</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-06-04T08:00:00</Start>
      <Finish>2027-06-17T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CLS Disc=PMG Resp=GC
Project closeout / demobilization — ensures Ready for Service and Final Completion are distinct (BSA standard tail).</Notes>
      <PredecessorLink>
        <PredecessorUID>8</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>10</UID>
      <ID>10</ID>
      <Name>Final Completion</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>MIL-00080</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-06-17T08:00:00</Start>
      <Finish>2027-06-17T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=MLS Disc=PMG Resp=OWN</Notes>
      <PredecessorLink>
        <PredecessorUID>51</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>9</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>11</UID>
      <ID>11</ID>
      <Name>Procurement</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>WBS-001.PRO</WBS>
      <OutlineNumber/>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-08-17T08:00:00</Start>
      <Finish>2027-03-03T17:00:00</Finish>
      <Duration>PT1080H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>12</UID>
      <ID>12</ID>
      <Name>Prepare and Submit Submittals — All Long-Lead</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>PRO-00010</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-08-17T08:00:00</Start>
      <Finish>2026-09-04T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT120H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=PRO Disc=PMG Resp=EPC
Submittals for pumps, switchgear, and generator prepared concurrently and submitted to engineer of record within 3 weeks of NTP.</Notes>
      <PredecessorLink>
        <PredecessorUID>3</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>13</UID>
      <ID>13</ID>
      <Name>Fabricate and Deliver Pumps and Motors</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>PRO-00020</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-09-08T08:00:00</Start>
      <Finish>2027-01-19T17:00:00</Finish>
      <Duration>PT720H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT720H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=PRO Disc=MEC Resp=VND
18-week lead time per narrative = 90 working days. Chain: NTP → submittals → approval (MIL-00020) → this activity → pumps on site.</Notes>
      <PredecessorLink>
        <PredecessorUID>4</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>12</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>14</UID>
      <ID>14</ID>
      <Name>Fabricate and Deliver Electrical Switchgear</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>PRO-00040</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-09-08T08:00:00</Start>
      <Finish>2027-02-02T17:00:00</Finish>
      <Duration>PT800H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT800H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=PRO Disc=ELE Resp=VND
20-week lead time per narrative = 100 working days after approved submittals.</Notes>
      <PredecessorLink>
        <PredecessorUID>4</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>12</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>15</UID>
      <ID>15</ID>
      <Name>Fabricate and Deliver Standby Generator</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>PRO-00060</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-09-08T08:00:00</Start>
      <Finish>2027-03-03T17:00:00</Finish>
      <Duration>PT960H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT960H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=PRO Disc=ELE Resp=VND
24-week lead time per narrative = 120 working days after approved submittals.</Notes>
      <PredecessorLink>
        <PredecessorUID>4</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>12</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>16</UID>
      <ID>16</ID>
      <Name>Pumps and Motors On Site</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>PRO-00030</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-19T08:00:00</Start>
      <Finish>2027-01-19T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=PRO Disc=MEC Resp=VND
Delivery milestone; gates pump installation.</Notes>
      <PredecessorLink>
        <PredecessorUID>13</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>17</UID>
      <ID>17</ID>
      <Name>Electrical Switchgear On Site</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>PRO-00050</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-02T08:00:00</Start>
      <Finish>2027-02-02T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=PRO Disc=ELE Resp=VND
Delivery milestone; gates switchgear setting and electrical rough-in.</Notes>
      <PredecessorLink>
        <PredecessorUID>14</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>18</UID>
      <ID>18</ID>
      <Name>Standby Generator On Site</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>PRO-00070</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-03T08:00:00</Start>
      <Finish>2027-03-03T08:00:00</Finish>
      <Duration>PT0H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>1</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT0H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=PRO Disc=ELE Resp=VND
Delivery milestone; gates generator pad and electrical connection.</Notes>
      <PredecessorLink>
        <PredecessorUID>15</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>19</UID>
      <ID>19</ID>
      <Name>Construction</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>WBS-001.CON</WBS>
      <OutlineNumber/>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-08-17T08:00:00</Start>
      <Finish>2027-04-14T17:00:00</Finish>
      <Duration>PT1320H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>20</UID>
      <ID>20</ID>
      <Name>Site Civil</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>WBS-001.CON.01</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-08-17T08:00:00</Start>
      <Finish>2026-11-25T17:00:00</Finish>
      <Duration>PT560H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>21</UID>
      <ID>21</ID>
      <Name>Perform Site Clearing and Grading</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00010</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-08-17T08:00:00</Start>
      <Finish>2026-09-04T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT120H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=CIV Resp=GC
Includes rough grading and clearing entire site footprint.</Notes>
      <PredecessorLink>
        <PredecessorUID>3</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>22</UID>
      <ID>22</ID>
      <Name>Install Site Drainage and Storm Sewer</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00020</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-09-08T08:00:00</Start>
      <Finish>2026-09-28T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT120H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=CIV Resp=GC</Notes>
      <PredecessorLink>
        <PredecessorUID>21</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>23</UID>
      <ID>23</ID>
      <Name>Install Security Fencing and Site Access Gate</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00180</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-09-08T08:00:00</Start>
      <Finish>2026-09-21T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=CIV Resp=GC
Perimeter security fencing; can proceed after rough grading complete.</Notes>
      <PredecessorLink>
        <PredecessorUID>21</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>24</UID>
      <ID>24</ID>
      <Name>Place Asphalt Paving and Concrete Flatwork</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00190</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-11-12T08:00:00</Start>
      <Finish>2026-11-25T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=CIV Resp=GC
Access road, parking, and equipment pad aprons; installed after all underground utilities complete.</Notes>
      <PredecessorLink>
        <PredecessorUID>22</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>35</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>25</UID>
      <ID>25</ID>
      <Name>Ground Storage Tank</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>WBS-001.CON.02</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-09-08T08:00:00</Start>
      <Finish>2027-01-04T17:00:00</Finish>
      <Duration>PT640H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>26</UID>
      <ID>26</ID>
      <Name>Excavate and Pour GST Foundation</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00030</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-09-08T08:00:00</Start>
      <Finish>2026-10-13T17:00:00</Finish>
      <Duration>PT200H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT200H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=CIV Resp=GC
1.5 MG prestressed concrete GST foundation slab and ring wall; allow cure time within duration.</Notes>
      <PredecessorLink>
        <PredecessorUID>21</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>27</UID>
      <ID>27</ID>
      <Name>Erect Prestressed Concrete GST Shell</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00040</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-10-14T08:00:00</Start>
      <Finish>2026-12-10T17:00:00</Finish>
      <Duration>PT320H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT320H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=STR Resp=SUB
Specialty prestressed concrete tank contractor; wire wrap and gunite included.</Notes>
      <PredecessorLink>
        <PredecessorUID>26</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>28</UID>
      <ID>28</ID>
      <Name>Install GST Roof, Hatches, and Appurtenances</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00050</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-12-11T08:00:00</Start>
      <Finish>2027-01-04T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT120H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=STR Resp=SUB
Includes overflow pipe, vent, level instrumentation rough-in, and interior coatings prep.</Notes>
      <PredecessorLink>
        <PredecessorUID>27</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>29</UID>
      <ID>29</ID>
      <Name>Pump Station Building</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>WBS-001.CON.03</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-09-08T08:00:00</Start>
      <Finish>2027-02-09T17:00:00</Finish>
      <Duration>PT840H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>30</UID>
      <ID>30</ID>
      <Name>Excavate and Pour Pump Station Foundation</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00060</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-09-08T08:00:00</Start>
      <Finish>2026-09-28T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT120H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=CIV Resp=GC
Includes pump base pads, equipment pads, and anchor bolts; can start concurrent with GST foundation.</Notes>
      <PredecessorLink>
        <PredecessorUID>21</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>31</UID>
      <ID>31</ID>
      <Name>Erect CMU Pump Station Building Structure</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00070</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-09-29T08:00:00</Start>
      <Finish>2026-11-03T17:00:00</Finish>
      <Duration>PT200H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT200H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=STR Resp=GC
2,400 SF CMU masonry walls and structural steel roof framing.</Notes>
      <PredecessorLink>
        <PredecessorUID>30</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>32</UID>
      <ID>32</ID>
      <Name>Install Pump Station Roof and Building Envelope</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00080</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-11-04T08:00:00</Start>
      <Finish>2026-11-25T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT120H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=ARC Resp=GC
Metal roof, louvers, doors, and weatherproofing; building must be enclosed before equipment set.</Notes>
      <PredecessorLink>
        <PredecessorUID>31</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>33</UID>
      <ID>33</ID>
      <Name>Set and Grout Vertical Turbine Pumps</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00090</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-01-20T08:00:00</Start>
      <Finish>2027-02-09T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT120H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=MEC Resp=SUB
Three 250-hp VTPs; requires building enclosed and pumps on site.</Notes>
      <PredecessorLink>
        <PredecessorUID>32</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>16</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>34</UID>
      <ID>34</ID>
      <Name>Yard Piping</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>WBS-001.CON.04</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-09-29T08:00:00</Start>
      <Finish>2027-03-17T17:00:00</Finish>
      <Duration>PT920H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>35</UID>
      <ID>35</ID>
      <Name>Install Yard Piping — 16-inch and 12-inch Mains</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00110</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2026-09-29T08:00:00</Start>
      <Finish>2026-11-10T17:00:00</Finish>
      <Duration>PT240H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT240H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=PIP Resp=GC
Approx 1,600 LF of 16-inch and 12-inch ductile iron yard piping; can proceed in parallel with building work.</Notes>
      <PredecessorLink>
        <PredecessorUID>21</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>22</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>36</UID>
      <ID>36</ID>
      <Name>Install Pump Station Piping and Valves</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00100</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-10T08:00:00</Start>
      <Finish>2027-03-10T17:00:00</Finish>
      <Duration>PT160H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT160H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=PIP Resp=GC
Suction and discharge headers, isolation valves, check valves, pressure gauges inside pump station.</Notes>
      <PredecessorLink>
        <PredecessorUID>33</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>37</UID>
      <ID>37</ID>
      <Name>Perform 16-inch Hot-Tap Tie-In to Transmission Main</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00120</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-11T08:00:00</Start>
      <Finish>2027-03-17T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT40H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=PIP Resp=GC
Hot-tap on live existing transmission main; requires district shutdown window coordination. Schedule as discrete activity after yard piping is complete. Confirm outage window with district operations. Removed dangling dependency reference to 'CON-00111' (no such activity) — review.</Notes>
      <PredecessorLink>
        <PredecessorUID>35</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>36</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>38</UID>
      <ID>38</ID>
      <Name>Electrical and I&amp;C</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>WBS-001.CON.05</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-03T08:00:00</Start>
      <Finish>2027-04-14T17:00:00</Finish>
      <Duration>PT400H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>39</UID>
      <ID>39</ID>
      <Name>Set Electrical Switchgear and MCC</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00130</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-03T08:00:00</Start>
      <Finish>2027-02-17T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=ELE Resp=SUB
Requires building enclosed and switchgear on site.</Notes>
      <PredecessorLink>
        <PredecessorUID>32</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>17</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>40</UID>
      <ID>40</ID>
      <Name>Install Electrical Conduit, Wire, and Lighting</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00140</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-02-18T08:00:00</Start>
      <Finish>2027-03-24T17:00:00</Finish>
      <Duration>PT200H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT200H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=ELE Resp=SUB
Building power distribution, lighting, receptacles, grounding, and utility service entrance.</Notes>
      <PredecessorLink>
        <PredecessorUID>39</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>41</UID>
      <ID>41</ID>
      <Name>Install SCADA Instrumentation and Field Devices</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00160</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-11T08:00:00</Start>
      <Finish>2027-03-31T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT120H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=EIN Resp=SUB
Flow meters, pressure transmitters, level transmitters, RTUs, and fiber/communication to district SCADA; requires piping and structural complete.</Notes>
      <PredecessorLink>
        <PredecessorUID>32</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>36</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>42</UID>
      <ID>42</ID>
      <Name>Set and Connect Standby Diesel Generator</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00150</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-03-25T08:00:00</Start>
      <Finish>2027-04-07T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=ELE Resp=SUB
Generator pad must be complete; generator on site required.</Notes>
      <PredecessorLink>
        <PredecessorUID>18</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>40</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>43</UID>
      <ID>43</ID>
      <Name>Complete Electrical Terminations and Motor Wiring</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>CON-00170</WBS>
      <OutlineNumber/>
      <OutlineLevel>4</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-01T08:00:00</Start>
      <Finish>2027-04-14T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CON Disc=EIN Resp=SUB
Final power and control terminations to VTPs and all equipment; requires pumps set and piping complete.</Notes>
      <PredecessorLink>
        <PredecessorUID>36</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>33</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>40</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>41</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>44</UID>
      <ID>44</ID>
      <Name>Commissioning and Closeout</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>WBS-001.COM</WBS>
      <OutlineNumber/>
      <OutlineLevel>2</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-15T08:00:00</Start>
      <Finish>2027-06-17T17:00:00</Finish>
      <Duration>PT360H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>1</Summary>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
    </Task>
    <Task>
      <UID>45</UID>
      <ID>45</ID>
      <Name>Perform Hydrostatic Testing — GST and Yard Piping</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>COM-00010</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-15T08:00:00</Start>
      <Finish>2027-04-21T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT40H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=COM Disc=MEC Resp=GC
Includes 24-hour hydrostatic test of GST per AWWA D110 and pressure testing of yard piping.</Notes>
      <PredecessorLink>
        <PredecessorUID>28</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>37</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>36</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>6</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>46</UID>
      <ID>46</ID>
      <Name>Perform SCADA Integration and Loop Checks</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>COM-00020</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-15T08:00:00</Start>
      <Finish>2027-04-28T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=COM Disc=EIN Resp=SUB
Point-to-point checks, motor wiring verification, loop checks, and integration test with district SCADA.</Notes>
      <PredecessorLink>
        <PredecessorUID>43</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>42</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>47</UID>
      <ID>47</ID>
      <Name>Perform Disinfection per AWWA C652</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>COM-00030</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-22T08:00:00</Start>
      <Finish>2027-04-28T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT40H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=COM Disc=MEC Resp=GC
Chlorination of GST, yard piping, and pump station per AWWA C652; includes flush, dose, hold, and neutralize.</Notes>
      <PredecessorLink>
        <PredecessorUID>45</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>48</UID>
      <ID>48</ID>
      <Name>Conduct Bacteriological Testing and Clearance</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>COM-00040</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-04-29T08:00:00</Start>
      <Finish>2027-05-05T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT40H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=COM Disc=MEC Resp=GC
Two consecutive satisfactory bacteriological samples required by state regulatory authority before service.</Notes>
      <PredecessorLink>
        <PredecessorUID>47</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>49</UID>
      <ID>49</ID>
      <Name>Perform Pump Start-Up and Performance Testing</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>COM-00050</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-06T08:00:00</Start>
      <Finish>2027-05-12T17:00:00</Finish>
      <Duration>PT40H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT40H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=COM Disc=MEC Resp=SUB
Wet run of all three VTPs, generator load test, and SCADA operational verification. Open end — no successor; auto-wired to Substantial Completion — review.</Notes>
      <PredecessorLink>
        <PredecessorUID>48</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
      <PredecessorLink>
        <PredecessorUID>46</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>50</UID>
      <ID>50</ID>
      <Name>Complete Punchlist and Final Inspections</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>COM-00060</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-05-13T08:00:00</Start>
      <Finish>2027-06-03T17:00:00</Finish>
      <Duration>PT120H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT120H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CLS Disc=PMG Resp=GC
Owner and engineer punchlist walkthrough, corrections, and final regulatory inspection.</Notes>
      <PredecessorLink>
        <PredecessorUID>7</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
    <Task>
      <UID>51</UID>
      <ID>51</ID>
      <Name>Deliver O&amp;M Manuals and Record Drawings</Name>
      <Active>1</Active>
      <Manual>0</Manual>
      <Type>1</Type>
      <IsNull>0</IsNull>
      <WBS>COM-00070</WBS>
      <OutlineNumber/>
      <OutlineLevel>3</OutlineLevel>
      <Priority>500</Priority>
      <Start>2027-06-04T08:00:00</Start>
      <Finish>2027-06-17T17:00:00</Finish>
      <Duration>PT80H0M0S</Duration>
      <DurationFormat>7</DurationFormat>
      <Work>PT0H0M0S</Work>
      <EffortDriven>0</EffortDriven>
      <Estimated>0</Estimated>
      <Milestone>0</Milestone>
      <Summary>0</Summary>
      <PercentComplete>0</PercentComplete>
      <RemainingDuration>PT80H0M0S</RemainingDuration>
      <ConstraintType>0</ConstraintType>
      <CalendarUID>1</CalendarUID>
      <Notes>BSA codes: Phase=CLS Disc=PMG Resp=EPC
As-built drawings, O&amp;M manuals, warranties, and spare parts delivery to district.</Notes>
      <PredecessorLink>
        <PredecessorUID>8</PredecessorUID>
        <Type>1</Type>
        <LinkLag>0</LinkLag>
        <LagFormat>7</LagFormat>
      </PredecessorLink>
    </Task>
  </Tasks>